The major conflict over Vlora Airport has taken an unexpected turn. A month after announcing the procedure for terminating the contract, it appears that the government has taken a step back by sitting down with the concessionaire and its owners to confront the parties' claims.
Kapitali has learned that the day before, the Ministry of Infrastructure held an official meeting with the concessionaire company Vlora International Airport and the lawyers of its two owners, Pacolli and Ademi.
Sources for Kapital said that the meeting took place in a positive atmosphere. Although no official decision has yet been made to terminate the contract termination procedure, the Ministry of Infrastructure and the concessionaire have agreed to consider a plan to resolve the conflict amicably.
According to sources, within a few days the concessionaire will submit a detailed plan to resolve the impasse, which will define the new schedule of works and the deadlines for their completion.
VIA will request the renewal of the construction permit, which expired a few months ago, and will provide guarantees for the completion of the works according to the plan, which it will present. Meanwhile, the ministry will decide whether the plan is convincing to resolve the impasse or whether it will continue with the contract termination procedure.
Kapitali has learned that the most interesting development in the meeting the day before was the agreement between the lawyers of the two conflicting shareholders, Pacolli and Ademi. Both parties have agreed that they will support the joint plan that VIA will present to the ministry, while the conflict between them and the claims they have against each other will be resolved in court without affecting the implementation of the plan. Pacolli's foreign lawyers, according to sources, have even agreed to recognize Vegim Hoxha as the company's administrator.
It remains to be seen whether this new development will lead to an amicable solution to the major gridlock at Vlora airport, something that has so far been seen as impossible.
The final decision now belongs to the government, which will have to calculate which path to choose, terminating the contract or reaching an agreement with the concessionaire, giving it a new opportunity to complete the construction of the airport under a new deadline, which could be extended by 8 to 10 months.
The calculation here is not simple. Even if the contract were to be terminated, this would still not guarantee the completion of the works in a faster time.
The government's decision to terminate the contract would be contested in the courts by the parties involved and would remain hostage to numerous legal processes, delaying the construction of the airport. Meanwhile, the solution would also carry the risk of arbitration.
All of this will become clearer in the coming days, but one thing is certain: The parties have begun negotiating in an attempt to find a solution.