The expansion of the Elbasan-Qafë Thanë road is rapidly turning into a bottomless pit for citizens' money. Official budget documents show that the costs of this work have spiraled out of control, inflated by constant contract modifications, poor management, and geological emergencies along the road.
What started as a step-by-step project has so far reached a bill of 35.2 billion lek, or over 387.8 million euros.
But this is not the end of the world. The total cost of the 51-kilometer road is likely to exceed 700 million euros, as contracts increase year by year.
The origins of the bloodshed
In late 2020, the Albanian Road Authority signed a contract with the company Infrakonsult for the Elbasan-Qafë Thanë road expansion project, part of Corridor VIII. Infrakonsult is the company of Redi Struga, a controversial businessman involved in the Zvërnec land scandal.
The project prepared by Infrakonsult was a pile of incomplete sheets and drawings, which not only did not detail how much the total cost of the road would be, but later proved disastrous for the state's finances.
Despite the project being problematic, the Albanian Road Authority rushed to begin construction of the road with the scheme of splitting it into 9 lots according to the scenario "let's start once and then see where it goes."
The first contract, for Lot I, was signed in September 2022 with the Alb Building company. The value of this contract was 2.18 billion lek or 24 million euros and included the expansion of a 5-kilometer segment.
A few months later, in early 2023, the government signed contracts for 3 more lots, while in 2024, those from lots 5 to 8 were also signed. According to the budget tables, the tenders for the 8 road lots were won with a total value of 21.8 billion lek or 240.5 million euros. But this was only the beginning of the pit.
A party for the companies
As soon as the machinery landed on the ground, the first consequences of the project began and the favorite party of the sharks who had won the tenders; the modification of the contracts.
The Road Authority began approving steep price increases for existing lots, under the pretext of unforeseen changes in the terrain.

For lots II, V and VI alone, the state budget was billed a direct addition of 1.7 billion lek, approximately 18.9 million euros, above the tendered value. But even this was just the beginning.
Geological emergencies
The biggest financial hole was opened by geological emergencies. The lack of serious studies of the soil layers before the start of works forced the government to take another 6.75 billion lek, or 73.3 million euros, from the budget for two new projects that "overgrow" as a result of damage to the ground.
First, the project for the "Revitalization of the slopes on the Elbasan - Bushtricës Bridge axis" will swallow up a full 4.2 billion lekë or about 46.2 million euros. The tender is scheduled for next year and the government has allocated the funds in the draft budget it has sent to Parliament.
This massive cost increase is justified to stabilize roadsides that are at risk of collapsing.
Second, and most scandalous, is the situation in Dragostunjë. After the road suffered a massive landslide blocking traffic, the Albanian Road Authority opened another emergency project titled "Stabilization of the landslide on the Librazhd - Qafë Thanë axis (Dragostunjë)". The bill for this intervention is 2.45 billion lekë or 27 million euros.

From the first to the eighth lot, the tendered value of the road was 21.8 billion lek or 240.5 million euros. But contract addenda and two geological emergencies increased the value by another 92.2 million euros above the tender value, bringing the total bill to 332.7 million euros for the 8 lots alone. But the well still has no end in sight.
Lot IX
Next year, the government will also hold a tender for Lot IX of the road. This segment includes the construction of a tunnel in the village of Hotolisht and has a cost of 5 billion lek or 55.1 million euros.
With this tender, the total cost of the 51-kilometer road reaches a full 387.8 million euros. However, the bill will continue to increase.

The road still has another untendered segment from Bushtrica to the border with Macedonia. Here there will be another tunnel, which will be financially shared between Albania and North Macedonia. It is not known how much this segment will cost to complete the road, which according to the ARRSH should have been completed next year.
But the deadlines have now been pushed beyond the medium-term budget, beyond 2029, however, this is not the only problem. The road has serious design problems, which will require billions more to fix. A source told Kapital that the cost could reach at least 700 million euros, while its quality and safety will continue to be a major challenge.
In short, Corridor VIII has become a huge financial hole, which is already consuming billions beyond any initial forecast. A situation identical to the Durrës-Kukës road, which was launched without a project and had extraordinary costs. But at least Durrës-Kukës was built with quality and continues to be in very good condition even after 15 years.
Elbasan Qafë Thanë will take billions to complete, but there is a risk of continuing the tradition of expensive roads that collapse as soon as they are inaugurated and that never finish, burning billions.