At the end of last year, the General Director, Eni Vasili, addressed the Ministry of Finance with an emergency request for an additional fund of 200 million lek, arguing that the public television was in deep financial crisis.
According to the request, RTSH is in critical conditions to fulfill its obligations, aggravated by the loss of millions of lek in the courts due to illegal dismissals of employees over the years.

But, while citizens are being asked to tighten their belts to save public television, the behind-the-scenes procurements tell a different story.
The money that Eni Vasili requested from the Parliament was allocated to the tender for the maintenance of the distribution network, where RTSH selected the winning bid that was 1.2 million euros higher than the lowest bid and 4.5 million euros more expensive than the bill for this service in the past 5 years. A criminal blunder.
The origins of a robbery
The 10 million euro tender for the maintenance of the RTSH distribution network was first opened in March of last year by former director Aurora Polo.
Three offers were submitted in the competition, the lowest of which was that of the company TBS 96 with 7.6 million euros. The company R&T offered a price of 8 million euros, while the third offer was that of the merger of the companies Idea Tel and Real Com, which offered a price of 9 million euros.
Polo was unable to complete the tender after he was dismissed from his post and Eni Vasili was appointed as the head of RTSH. Three days after taking office, Vasili decided to disqualify all three bids and cancel the tender. But this decision was appealed to the KPP by the company TBS 96 and R&T.
The Public Procurement Commission rejected Vasili's decision to cancel the tender and ordered RTSH to declare the winner the company R&T, which had offered 8 million euros.

R&T's announcement of the winner by the KPP
But Albanian Radio Television did not implement the decision of the Public Procurement Commission, even though this was a legal obligation, canceling the tender again with the argument that the company declared the winner by the Public Procurement Commission did not prove that it had not been convicted.

VAT's argument for non-implementation of the KPP decision
However, the courageous actions of RTSH were later met with criticism.
In bed with Idea Tel
The RTSH war apparently had a goal. It was the company Idea Tel, which always offered the highest value, at the head of the limit fund.
After the cancellation of the first tender, RTSH re-announced the maintenance tender. This time, RTSH changed the criteria by introducing as a necessary condition the authorization of the manufacturer for the antenna equipment, even though there was a decision by the Supreme Audit Office, which ordered that authorization not be required since it predetermined the winner.
In the second tender, three offers were submitted, but one of them was fictitious and was submitted by Idea Tel itself. The two companies, TBS 96 and R&T, entered together with the offer of 787 million lek or 8.65 million euros at the current exchange rate. While the Idea Tel company offered the price of 899.3 million lek or about 9.9 million euros, that is, 99.3 percent of the limit fund.
Setting the authorization criteria was key to bringing the tender to Idea Tel. This company had created a short circuit with Rohde & Schwarz, the German company that had built the RTSH antenna network. This was the reason why Idea Tel always offered at the top of the limit fund, after receiving guarantees that it would be the winner.
Authorization intrigues
Idea Tel had authorization from Rohde & Schwarz. The merger of the companies R&T and TBS 96, presented authorization from a Chinese company, called Xiamen General Electronic, which was an authorized distributor of Rohde & Schwarz.
After the tender was held, intrigues began. RTSH asked the Chinese company for confirmation whether its authorization was original. This unusual action had a great intrigue behind the scenes. Idea Tel had lobbied Rohde & Schwarz to force the Chinese company to withdraw the authorization.
In its first response to RTSH, the Chinese company denied authorization. As soon as the response arrived, Eni Vasili immediately disqualified the bids of the two companies R&T and TBS 96 with the argument of forgery, declaring Idea Tel the winner.
But later the Chinese resend another response, confirming that the authorization they had issued to the two companies was not fake, but was original and legitimate. However, they decided to revoke it, arguing that they had been authorized by Rohde & Schwarz only for the territory of China.

Revocation
The unusual action of RTSH to seek confirmation from the Chinese company seems to have been pushed and coordinated by the one holding the reins of Rohde & Schwarz. This was Idlir Karkini, the owner of the company Idea Tel, which had previously been their subcontractor. Everything would become clearer later.
Internal accusations of corruption
While RTSH was announcing the winner of the Idea Tel company, Kapitali published a bombshell accusation from a member of the VAT Tender Commission. One of the 5 members of the KVO, appointed by RTSH itself, denounced that the value of the tender that was won by Idea Tel, owned by businessman Idlir Karkini, was inflated by 60 percent compared to the price that the same service cost in the previous four years.
"The same operator (Idea-Tel) has subcontracted the service for the period 2021-2025 at a price of 5.6 million euros excluding VAT. Meanwhile, for the same service (same period and work object) it has offered 9 million euros or 61 percent more," states the denouncing opinion, which the KVO member has attached to the winner's evaluation.

Bombshell denunciation of KVO member
The tender limit fund for the maintenance of RTSH's DVB-T2 distribution network for a period of four years was predetermined at 906 million lek. Idea-Tel and Real Com were declared winners with the price of 899.3 million lek or 99.3 percent of the limit fund. That is, in a tender of 10 million euros, RTSH saved only 70 thousand euros. These prices are offered only when the tender does not have competitive pressure and the predetermined winning company is not afraid of competition.
But the inflated fund was not the only issue. The KVO member denounced that the winning company did not even meet the criteria. "Idea-Tel and Real Com lack university diplomas for four engineers and employment contracts for all declared staff. Also, based on the information in the file, it cannot be proven whether the engineering staff of both companies has work experience related to DVB-T2 systems," the letter continues.
Despite strong objections from one of the KVO members, the General Directorate of RTSH declared the merger of the companies Idea-Tel and Real Com the winner in a procurement process without competition and with an inflated value almost twice.
This entire farce was certified by the KPP, which refused to open the papers of the company declared the winner to verify whether or not it met the conditions.
Who is responsible?
This tender raises serious questions about the integrity of RTSH's fund management. How can a public institution that claims to be on the verge of bankruptcy refuse to save 1.2 million euros and accept an inflated offer of 4.5 million euros more than the previous contract?
Eni Vasili has announced an in-depth audit of the company's finances over the years. But with the certification of this latest tender, the schemes of extortion of public money are continuing before the eyes of the control institutions.
RTSH is an institution tainted by corruption. A public television, which asks for additional money from citizens to finance abuses in public tenders.