Greed does not stop/ DPSHTRR builds headquarters with 1750 euros per square meter without land costs

Greed does not stop/ DPSHTRR builds headquarters with 1750 euros per square

The General Directorate of Road Transport has announced the modification of the contract for the construction of the new building of this institution. According to documents published in the Public Procurement Agency, the cost of the construction of the building will be increased by 142.3 million lek or 1.5 million euros above the contracted price in the tender. This brings the total cost of the new DPSHTRR building to a full 9.3 million euros.

It is not known how the cost increase of 20 percent above the level contracted in the tender was justified, as the full tender documentation, which is expected to be announced soon, has not yet been published.

But post-tender cost increases are a widely used practice in public tenders in Albania, thanks to a legal clause that allows contract additions of up to 20 percent of the tender value.

The tender for the construction of the new DPSHTRR building was held in the summer of 2023 with a predetermined limit fund of 785 million lek. The winner of this tender was the company Hastoçi, which offered a price of 737.5 million lek.

Greed does not stop/ DPSHTRR builds headquarters with 1750 euros per square

But now that the building should have been completed, the DPSHTRR has decided to add another 142.3 million lek on top of the tender price, bringing the total cost of building construction to 9.3 million euros, not including value added tax.

If the total cost of building the DPSHTRR headquarters is included, it will reach 11.2 million euros. According to the project, this building will have a total area of ​​6,385 square meters, of which 2,400 meters are underground basements.

This means that DPSHTRR is paying a full 1,750 euros per square meter for the construction of its headquarters, without the cost of the land that belongs to the state, which constitutes an absolute record of greed and waste of public money.

Suspicious tender

The tender for the new DPSHTRR building has been held twice. The first time the competition was opened in November 2022. 7 offers were submitted, the lowest of which was the merger of the Curri and Agri Construction companies with 700 million lek. But the DPSHTRR decided to disqualify all offers.

The matter was appealed to the Public Procurement Commission. After a delay of several months in reviewing the matter, the latter found the complaints of the companies with the lowest bid for unfair disqualification partially justified, but through a strange decision ordered the DPSHTRR to cancel the tender and reopen the competition.

In the second tender, DPSHTRR announced the winner of the Hastoçi company with a bid of 737.5 million lek, to which another 142.3 million lek will now be added.

Editorial