The Albanian Government officially launched the process of public consultations and stakeholder engagement for the Murriqan-Balldrenë highway project.
This 41-kilometer axis constitutes the first segment and gateway of the Adriatic-Ionian Corridor in Albanian territory, which will connect Albania with Montenegro through an infrastructure of high European standards.
The project, which passes through the territory of the municipalities of Shkodër, Vau i Dejës and Lezhë, aims to replace the existing low-standard road with a modern Category A highway.

It will have four lanes (two in each direction), fully fenced for safety, and a designed speed of 120 km/h.
Part of the project are also 5 level crossings (Murriqan, Velipojë, Vau i Dejës, Gjadër and Balldren), as well as the construction of a new major bridge over the Buna River.
Not a concession, but a classic public tender in 2027
One of the most important details that the documents clarify is that this highway will not be built through a concession or through Public-Private Partnership schemes, like the rest of it from Balldrena to Fier. The project will be implemented through direct state procurement.
The financing is expected to be covered by the state budget and the European Bank for Reconstruction and Development as the main financier, also supported by grants and technical assistance from the European Union through the Western Balkans Investment Framework (WBIF).
According to the official works calendar, the drafting of the Detailed Implementation Project and the preparation of the environmental package began in June 2025 and have a timeframe of 24 months.
This process is expected to fully conclude the technical documentation in June 2027. Immediately after this deadline, the ARA will announce the international tender for the selection of the company that will carry out the physical works on the ground, paving the way for the start of the construction of the Highway.
The launch of the consultation phase comes in parallel with the updates to the Environmental and Social Impact Assessment. Given that the highway route lies mainly in agricultural plain areas, official documents confirm that a socio-economic survey of residents affected by the project has begun.
To avoid the isolation of communities, the project envisages the construction of an entire network of local roads and underpasses for pedestrians, agricultural vehicles and livestock.