The reconstruction of the Tirana-Durres secondary road begins, the 4.3 million euro tender for the Hygea Megatek segment closes

The reconstruction of the Tirana-Durres secondary road begins, the 4.3 million

The Municipality of Tirana has concluded the tender procedure for the project "Reconstruction of the Tirana-Durres secondary road for the segment from Hygea Hospital to Megatek", announcing the winner of the joint venture of economic operators "Vëllezërit Hysa" sh.pk & "Ergi" sh.pk

The value of the selected bid is 4.3 million euros (386,510,064.08 lekë). This bid was qualified as the one with the lowest price among the operators that met the technical criteria, while the deadline set for the completion of the works is 5 calendar months from the signing of the contract.

The road axis in question has a length of about 6.8 kilometers and runs parallel to the Tirana-Durrës highway, from the "Hygea" hospital roundabout to the Rinas overpass.

The reconstruction of the Tirana-Durres secondary road begins, the 4.3 million

This segment serves as an access road for the industrial area and surrounding villages (such as Laknas and Domje), as well as to ease the traffic flow on the highway. The existing condition of the axis is characterized by significant damage to the asphalt layers, 70% worn-out sidewalks, and a lack of efficiency in the public lighting network and rainwater drainage.

According to the project implementation, the technical intervention will include excavating the existing structure and laying a new road package with four layers: asphalt, binder, bituminous conglomerate and stabilizer.

The new carriageway will be 6.5 meters wide, divided into two lanes of 3.25 meters in each direction. In parallel, the sidewalks will be reconstructed with self-compacting concrete slabs and accessibility ramps, and ornamental trees will be planted every 6 meters.

Regarding underground infrastructure, rainwater will be managed through new manholes that will discharge into the concrete channel that ARRSH is building parallel to the highway.

Also, a new LED lighting network with poles every 28 meters, new underground lines for telephony and fiber optics, as well as a dedicated MNZ network with underground hydrants every 100 meters will be installed.

Editorial