Since the conflict between the two shareholders at Vlora Airport erupted, Albanian citizens have been bombarded with pompous figures about the investment in this project. But what is the truth according to official documents?
Data from the official balance sheet shows that by the end of last year, the total assets of the concessionaire company VIA reached 8.8 billion lek or 94 million euros at the current exchange rate.
This figure represents the maximum amount invested in Vlora Airport until December 2025. But the real figure is lower, as within this amount there is also 1 billion lek or almost 11 million euros in VAT that the company must reimburse back from the state.
But how were these investments financed?
According to the financial statements, 5.9 billion lek were financed by a loan that VIA received from BKT.

Another 2.6 billion lek are works carried out by the 2A Group company, but not yet paid by VIA.

Meanwhile, Behgjet Pacolli has financed 535 million lek or 5.7 million euros through a loan that his company Mabco has given to VIA as a partner. Initially, Mabco gave VIA a loan of 11 million euros, but has withdrawn half of it. However, the remaining 5.7 million euros is still a loan, which VIA must repay to its partner Mabco.

This is a picture of the investments and their financing in Vlora Airport. So 60 million euros of BKT's loan, 27.5 million euros of Valon Ademi's 2A Group, and 5.7 million euros of Pacolli's Mabco loan.
But each party has its own way of interpreting these figures. Behgjet Pacolli says that the entire investment was financed by him. Mr. Pacolli says that the loan at BKT is his, as it was taken out by leaving Mabco's assets and his personal assets as collateral.
The debt of 27.5 million euros that VIA has towards 2A Group for completed but unpaid works, is also Pacolli's financing, as he says that this money will be repaid to Ademi's company. Meanwhile, Mr. Ademi insists that he has 49 percent of the shares according to the sales contract and that the unpaid works also reflect this fact.
But despite the claims of the two shareholders, in the end the financing of the airport was done by the concession company itself.
If the government terminates the concession, the loan will remain with the state, meaning it will be paid by taxpayers or the new shareholder who will receive the concession. The same applies to any other obligation of the concessionaire company, including debts for unpaid works of 2A Group and the 5.7 million euro loan of Pacolli.
In the end, the company itself is guaranteed by taxpayers' money, as the state budget has undertaken to guarantee 136 million euro of income for the first 10 years of operation, as a traffic guarantee.
The only question remains that of the properties that Pacolli has left as collateral in BKT. What happens to these properties after the two current partners are removed from the concession. This will depend on how this conflict is resolved. Normally, taking over the concession from the state would have to release Pacolli's properties from encumbrance, as BKT would be guaranteed by the state or the new concession shareholder.
There are many scenarios for how the concession issue could be resolved. From a purchase agreement at book value to expropriation for breach of contract. But one thing is certain.
The fault for why the airport was not built is not even the government's, and even less the Albanian taxpayers'. The fault lies with those who are now threatening with 700 million euros in arbitration and lost profits. Yes, the government is deeply guilty. Giving strategic projects to controversial businessmen who only know how to play the realtor's game.