The independent engineer recommended that the government withdraw from the termination of the Vlora Airport concession. The company, which was contracted by the government itself to supervise the works at the airport, has recommended through an official letter to the Ministry of Infrastructure to stop the termination of the contract and sit down in negotiations with the parties to resolve the problem.

"At this stage, we cannot technically support the early termination of the Contract without first examining, through the contract mechanisms, the possibility of a controlled continuation of the works," the engineer states in a letter dated August 25.

The Albanian government based the termination of the concession contract on the failure to meet the operating date, i.e. the failure to put Vlora airport into operation according to the deadlines provided for in the contract.
But the independent engineer says that the project delays are not solely the fault of the concession company, but some of them also stem from administrative reasons related to the actions or inactions of the government, while others are related to causes that are beyond anyone's control, such as climatic factors.
"In the government's announcement of the contract termination, we do not find a final analysis that separates and measures the impact of contractor delays, technical project changes and phase merging, work restrictions due to non-extension of the construction permit, physical obstacles and site safety...," the engineer continues.

On June 23 of this year, the independent engineer recommended to the Ministry of Infrastructure to postpone the airport's completion deadline by 43 weeks, according to a defined work plan, which also formalized the merging of construction phases.
According to this plan, the airport would begin operating within 14 weeks, while the remaining time for weeks 15-43 would serve to complete the work of other phases.
At the same time, the engineer recommended that this plan serve as the basis for the implementation, monitoring and reporting of the works. If the concessionaire did not adhere to the new plan, then, according to the engineer, the government would have the unchallenged right to terminate the contract.
But the government went ahead with the contract termination despite this recommendation. This is a significant risk for Albania in the Court of Arbitration, as the independent engineer's letter serves as strong evidence in favor of the concessionaire.
Currently, VIA, as well as its shareholder Mabco, have officially opened arbitration against the Albanian government in London, where the first phase is a request to block the termination of the contract. Meanwhile, after overcoming this phase, the parties will present claims for financial damages.
This is a delicate process, because if the government does not scrutinize its papers and actions in an exemplary manner, then Albanian taxpayers could pay dearly, and in this case, it is a bill of hundreds of millions of euros.