The Ministry of Infrastructure and Energy says that it is the winner of the trial for the security measure on the termination of the Vlora Airport concession and that the concessionaire has only received a temporary relief measure. Through a press release, the MIE said that the London Arbitration dismissed two of the three claims of the concessionaire company VIA.
"The decision constitutes an important victory for the Ministry of Infrastructure and Energy. The Emergency Arbitrator completely dismissed two of VIA's three requests and did not accept VIA's main request, namely the suspension of the termination of the Concession Contract," the MIE stated through an official press release.
According to the MIE, the concessionaire's only victory was a temporary security measure.
"The only relief granted was a short-term interim measure. The Emergency Arbitrator ordered MIE to temporarily refrain from exercising certain rights arising from the termination of the Concession Contract. The Arbitrator emphasized that the measure is short-term and will remain in force only until the arbitration tribunal is constituted and able to consider the matter," MIE stated.
According to her, this temporary measure does not affect the termination of the concession contract.
The full statement of the Ministry of Interior:
Emergency Arbitration Dismisses VIA's Main Claims and Declines to Suspend Termination of Concession Contract
On September 16, 2026, the Emergency Arbitrator issued the Order in the context of emergency arbitration proceedings initiated by VIA, the Concessionaire under the Vlora Airport Concession Contract.
The decision constitutes a significant victory for the Ministry of Infrastructure and Energy. The Emergency Arbitrator dismissed two of VIA’s three claims in their entirety and did not accept VIA’s main claim, namely the suspension of the termination of the Concession Contract. The only measure ordered was the limited and temporary maintenance of the status quo, until the arbitration tribunal is constituted and able to consider the case.
Most importantly, the Arbitrator dismissed VIA’s main claim to suspend both the termination of the Concession Contract and the enforcement of the Notice of Settlement, under the broadly extra-contractual terms sought by VIA. The Emergency Arbitrator agreed with MIE that neither the Contract nor the evidence presented provided a sufficient legal basis to do so.
As a result, the termination of the Concession Contract has entered into force.
The arbitrator also dismissed VIA’s requests to compel MIE to participate in mediation and to appoint a mediator, as well as to postpone the start of the arbitration for a further two months. The dismissal of these requests confirms that the dispute, in which MIE will continue to vigorously defend its position, can now proceed immediately to the arbitral tribunal.
The only relief granted was a short-term interim measure. The Emergency Arbitrator ordered MEI to temporarily refrain from exercising certain rights arising from the termination of the Concession Contract. The Arbitrator emphasized that the measure is short-term and will remain in force only until the arbitral tribunal is constituted and able to consider the matter. The short-term measure does not affect the validity or effectiveness of the termination of the Concession Contract.
In light of these findings, the Emergency Arbitrator also ordered VIA to bear the costs of the emergency arbitration proceedings.
The decision therefore represents a clear failure by VIA to secure the award that formed the essence of its claim.
VIA sought to prevent the entry into force of the termination of the Concession Contract and to delay the commencement of the arbitration through a protracted mediation process. It achieved neither. The termination of the Contract was not suspended, the requests for mediation and extension of time were dismissed, and the only request granted is a short-term measure maintaining the status quo until the arbitral tribunal is constituted and can consider the matter itself.
The decision enables the MEI to prepare the further steps arising from the termination of the Concession Contract, which are necessary to protect the public interest, while fully respecting the limited and short-term measure ordered pending the constitution of the arbitration tribunal and its decision on this matter.
In accordance with the decision of the Emergency Arbitrator, the MEI will notify VIA today that the termination of the Concession Contract has entered into force.