Lajme nga vendi

Koray of Kurum buys Lengarica hydroelectric power plant

Koray of Kurum buys Lengarica hydroelectric power plant

The Lengarica hydroelectric power plant, one of the most controversial projects for its environmental impact, has changed hands. The Austrian group ENSO has sold the plant to the company Albasteel, which is owned by Koray Zeytinoglu, otherwise known as Koray of Kurum, due to his close ties to the steel company.

The purchase amount has not been made public, but Kapital has learned that it is a transaction of around 15 to 20 million euros.

Built a few meters above the famous Lengarica canyon, the hydroelectric power plant of the same name has an installed capacity of 8.9 megawatts. According to data from the Energy Regulatory Authority, this plant has an annual production that fluctuates between 20 and 30 thousand megawatts of energy per year, generating about 2.3 million euros in revenue per year.

Koray Zeytinoglu is one of the most important figures within the Turkish company Kurum. For 20 years he has held the position of administrator of Kurum, and most recently he is the main advisor of this company.

Koray of Kurum buys Lengarica hydroelectric power plant

Koray Zeytinoglu

In the summer of 2017, Zeytinoglu was arrested by the Elbasan Prosecution Office on charges of creating fraudulent schemes with VAT refunds, causing economic damage to the state worth around $1.5 million.

According to the prosecution's file in 2017, Koray Zeytinoglu in his capacity as administrator and the former director of Scrap in Kurum, Yucel Aksu, through fictitious invoices, had declared that purchase and sale activities in 2011 with the companies Kurbini shpk, Erad&XHT, R&B2011 and Kavaja Co.

But Zeytinoglu was released from prison a few days later and the charges began to evaporate along the way, especially the one for money laundering. Now the arrested former administrator of Kurum is making a strong return to the business scene by purchasing an important asset, such as the Lëngarica hydroelectric power plant.

The
concession for the construction of the Lengarica hydroelectric power plant was awarded in 2008 to an unknown Albanian company, called Hasi Energji, owned by two shareholders, Astrit Dhromaj and Hasan Leka.

With the concession in hand, Hasi Energji created a joint venture with the Austrians Enso Hydro called Lengarica & Energy in 2011. Hasi Energji initially transferred 20% of the concession shares to the Austrians Enso and then sold them all for 800 thousand euros.

On August 3, 2011, Enso Hydro took control of all shares of Lengarica & Energji. It is estimated that Hasi Energji spent 15,000-20,000 thousand euros on the concession before selling it to the Austrians "Enso" for 800 thousand euros.

Environmental massacre
After Enso Hydro took full control of the company "Lengarica & Energy", the project for the construction of a single hydroelectric power plant with a capacity of 8.9 MW moved forward on the Lengarica River.

To finance the project, the Austrian company secured financing from the World Bank's IFC and a German commercial bank, while field work began in the summer of 2013, despite strong opposition from local environmental groups.

The hydroelectric power plant in the area of ​​the famous Bënja spa was built even though Sali Berisha's government had declared the Hotovë-Dangëllija area a National Park in December 2008, but only after the Hasi Energji company had been approved for concession and environmental permits.

The Lëngarica hydroelectric power plant uses 8 cubic meters of water per second from the total flow of the river of the same name, leaving only 0.2 cubic meters per second to flow into the canyon.

Editorial