The entrance to Tirana for those coming from the North will change radically, marking the end of the long traffic nightmare in the center of Kamza and at the Lapraka bend.
The Albanian Road Authority has taken the first official steps towards the construction of a New Northern Entrance, a strategic axis of about 17 kilometers that will divert all transit vehicle flow directly to the capital's Grand Ring Road.

The new project, which is expected to be financed from the state budget during the years 2026-2028 with an initial limit fund of 1.8 million euros for the design phase alone, will definitively change the traffic map at the entrance to Tirana.
How will travel from the North change?
Until now, any vehicle coming from Shkodra, Lezha or Kukës was forced to pass through the center of Kamza and get stuck at the Kamza Turn. With the new axis, this route is eliminated.
The new road will function as a four-lane main interurban road and will follow this new alignment:
• Departure: Vehicles coming from the Thumanë–Kashar highway will immediately divert to the southern part of the Rinas junction (Km 0+000).
• Route: The road will pass through the outskirts through the fields of Valias and Zallherri (near the Military Department), completely bypassing the residential area and the center of Kamza.
• Conclusion: The new axis will exit directly at Paskuqan, organically connecting to Lot 7 of the Tirana Ring Road.
Direct connection to Elbasan and Corridor VIII
In addition to avoiding Kamza, this change brings a great advantage for vehicles destined for the southeast of the country.
Drivers coming from the North can enter the Grand Ring Road in Paskuqan and exit directly onto the Tirana-Elbasan highway (Corridor VIII) without stopping at any traffic lights and without entering the internal roads of Tirana at all.
According to the ARA Terms of Reference, the design companies have a deadline of 10 months to draft the Concept Project (where two route variants will be considered) and another 8 months for the detailed Implementation Project.
Following the approval of the expropriation reports and the Environmental Impact Assessment (EIA), the project will be opened for tendering of field works.